TL;DR: “Smart panel” is not a scope of work. First determine whether the caller wants app control, a way to address a solar or EV service upgrade, or battery backup. Those are three different jobs with three different quoting paths.
The caller may be naming a product, not a job
SPAN sells five panel models: MAIN 16, MAIN 32, MAIN 40, MLO 24, and MLO 48. SPAN advertises 16 to 48 controllable circuits.
That tells you the brand name the customer saw. It does not tell you what work the customer needs.
On a call, “smart panel” tells you the product category, not the scope. The first questions are the panel and service size, whether solar, a battery, or an EV charger is involved, and whether another contractor has already quoted the work.
Wirewoman’s intake follows that order. The job summary puts those answers in a short list so you can see which of the three jobs this is before you call back.
That distinction matters. A customer asking for an app controlled panel may need a panel replacement. A customer trying to avoid a service upgrade may need a load calculation, code review, utility discussion, and permit. A customer who wants the house to run during an outage is asking for a battery system.
Do not quote all three from the words “smart panel.”
SPAN’s MAIN 32 has specifications you need before you quote
SPAN’s own product pages identify the MAIN 32 as a panel with 32 controllable circuit spaces. Its listed main breaker rating is 100 to 200 amps. The busbar rating is 225 amps. The panel has feed through lugs and a NEMA 3R enclosure for indoor and outdoor use.
The same page shows these listings:
- UL 67
- UL 916
- UL 869A
- UL 3141 [PCS]
Those details do not answer every California plan check question. They tell you what the manufacturer lists for that model.
The MLO 24 is different in a way that affects the material list. It has 24 controllable circuit spaces and a 225 amp busbar rating. Under “Required equipment (not included),” SPAN lists a 100 to 200 amp main breaker.
MLO means main lug only. The installer supplies a separate main breaker. If the caller has an MLO model in mind, do not price it like a MAIN model.
There is another model restriction. The MAIN 32 page says it is compatible only with other MAIN 32 panels for multi panel installations. If the customer is discussing multiple panels, get the exact model before you discuss the equipment package.
If the caller wants app control
The first caller may mean, “I want to see and control my circuits from an app.”
That is a convenience upgrade. The scope is a whole panel replacement with the SPAN hardware and the installation work required for that replacement. The app control is the product here.
SPAN says the SPAN Home App provides real time on and off control of every circuit. That is the feature the caller is asking to buy. It is not automatically a service upgrade solution or a backup power system.
Your quote still depends on the existing panel, service, location, permit, and installation scope. Do not turn “smart” into a promise about the home’s available capacity.
The price question needs the same discipline. SPAN’s own page says panels start at $2,550, plus installation, taxes, and shipping. Other websites show different figures for the same product, including figures around $3,500.
Use the price from your distributor or from SPAN at the time of the quote. Do not give a total installed price from this article. The installed total depends on the existing service, the permit, and the scope.
The SPAN pages reviewed for this piece did not state a warranty. They also did not say whether a particular jurisdiction will accept the panel’s control settings as a way to avoid a service upgrade.
A smart panel does not settle a California service upgrade
The second caller may say, “My solar installer or EV charger quote says I need a service upgrade. I heard a smart panel avoids that.”
That is a code and utility question, not a product question.
Whether current limiting control can let you add a battery or EV charger without a service upgrade is a 705.13 and 750.30 question. Section 750.30 recognizes only listed systems and requires specific field marking.
California enforces the 2025 California Electrical Code, based on the 2023 NEC, effective January 1, 2026. The code path is covered in this article on 705.13 energy management systems and power control systems in California.
Do not tell a customer that SPAN’s UL 3141 listing automatically satisfies a California plan checker. It does not give you that answer by itself. Confirm with the building department how they want the system documented.
You also need the load calculation, the proposed equipment, the service details, and the permit status. Ask who is installing the solar or EV equipment and whether that contractor has already pulled a permit. A panel product page cannot replace those facts.
For the broader intake questions that apply to panel upgrade calls, use what to ask before you book a panel upgrade call. For an EV driven call, use what to ask before you book an EV charger installation.
Backup power means a battery job
The third caller may say, “I want the house to keep running when the power goes out.”
That is a battery job. The panel is one piece of it.
SPAN lists compatibility with Tesla Powerwall, Franklin aPower, SolarEdge, and Enphase batteries. Its FAQ lists model specific requirements. Ask which battery the customer has or plans to install before you say yes.
Do not treat “battery compatible” as a complete scope. You still need the existing panel and service information, the panel location, the battery brand, and the roles of the other contractors. The battery and the panel must be considered together.
The backup power intake is covered in what to ask before you book a solar and battery backup call.
If the caller mentions an EV charger at the same time, sort that work separately. The charger may be the reason someone is asking about control, load management, or a service upgrade. That puts the call back into the 705.13 and 750.30 discussion, with the permit and building department questions attached.
Ask these questions before you put a number on it
-
Why do you want a smart panel? This separates app control, a service upgrade question, and battery backup.
-
What is the current panel, service size, brand, and age? You need the existing equipment before you can judge a panel replacement or service scope.
-
Do you have, or have you been quoted, solar, a battery, or an EV charger? Ask who is installing it and whether that contractor has already pulled a permit because the related project may control the code and permit path.
-
Which battery brand is involved? SPAN’s battery compatibility and requirements are model specific.
-
Is the panel indoors or outdoors, and where is it located? The installation location affects the equipment and the work required.
-
Do you have home internet near the panel? SPAN requires an internet connection to control the panel. Cellular backup is available, but SPAN says it should not be relied on as the primary connection.
-
Do you know the panel must be commissioned by a SPAN Authorized Installer? SPAN says, “You must be a SPAN Authorized Installer in order to successfully install and commission SPAN Panels with the SPAN Installer App.” If your shop is not authorized, say so up front and refer or decline the commissioning work.
That last question belongs in the first call. It is not a detail to discover after the equipment arrives.
The internet and installer requirements are part of the scope
SPAN’s panel page says an internet connection is required to control SPAN. Cellular backup is available, but it should not be relied on as the primary mode of connectivity.
That means the panel location matters beyond the enclosure. Ask whether home internet is available near the panel before you promise app based control. The customer is not buying the same experience if the required connection is missing.
Commissioning is another scope boundary. Installation and successful commissioning are connected in SPAN’s own instructions. If your shop is not a SPAN Authorized Installer, the customer needs to know that before the quote becomes a purchase order.
Say what your shop will do. Say what it will not do. Refer the commissioning portion when necessary.
Wirewoman can sort the call after hours
Wirewoman answers 24/7, books to the shop’s calendar, sends the job summary to the shop by SMS within 30 seconds, and logs every call to a dashboard.
She can ask these sorting questions on every smart panel call, including after hours. The owner reads the answers instead of a voicemail that says, “Call me about a smart panel.”
That changes the callback. You can see whether the caller wants app control, is responding to a solar or EV service upgrade quote, or is asking for battery backup. You can see the current panel and service information, the proposed equipment, the battery brand, and whether another contractor is already involved.
Change the first call before you change the panel
Do not start by quoting a smart panel.
Start by asking why the customer wants it, what equipment is already there, and whether solar, a battery, or an EV charger is involved. Get the exact model if the customer has one. Confirm internet access and SPAN Authorized Installer status. For service upgrade questions, open the 705.13 and 750.30 path and confirm the building department’s documentation requirements.
Then quote the actual job in front of you.