TL;DR: For private construction contracts signed on or after January 1, 2026, a California electrical contractor can owe unpaid labor costs incurred by a subcontractor at any tier. Periodic payroll reviews, corrective action after notice, and a final affidavit can protect you from penalties and liquidated damages, but they do not erase liability for unpaid wages and interest.
Your contract with the owner makes you the direct contractor
Labor Code section 218.9 applies to private construction contracts entered into on or after January 1, 2026. If you contract directly with the owner for the erection, construction, alteration, or repair of a building, structure, or other private work, you are the direct contractor.
That includes a homeowner, business owner, or landlord who signs your contract for a service upgrade or remodel. It can include a small electrical shop that hires another shop for overflow, or hires a trenching, concrete cutting, drywall, stucco, or low-voltage subcontractor.
The statute says the direct contractor “shall assume, and is liable for, any indebtedness for the performance of labor” incurred by a subcontractor at any tier acting under, by, or for the direct contractor. The covered debts are those described in Civil Code section 8024(a).
This is private work only. Section 218.9 does not apply to work performed by an employee of the state, a special district, a city, a county, a city and county, or another political subdivision of the state. The text does not exclude residential or single-family work.
If a general contractor hired you for a tenant improvement, the GC is the direct contractor. You are the subcontractor. If you hired a lower-tier sub, you may be the direct contractor as to that sub.
California already had a direct-contractor wage liability rule under Labor Code section 218.7, added by AB 1701 in 2018. SB 597 added section 218.9 after a superior court ruling involving federal ERISA preemption and trust funds collecting unpaid fringe contributions. The Assembly passed SB 597 by a 79-0 vote. The Senate passed it on concurrence by a 40-0 vote in September 2025.
Your exposure is labor debt, not every dollar the sub claims
Section 218.9(a)(1) limits your liability to payments for labor required by the subcontractor’s agreement with the laborer or the subcontractor’s collective bargaining agreement.
That limit matters. The statute concerns labor indebtedness. It does not make you responsible for every disagreement between the sub and its workers.
But section 218.9(a)(2) adds more than unpaid labor. The direct contractor’s liability can include the unpaid labor, penalties or liquidated damages, and interest owed by the subcontractor because of the labor performed.
The three compliance steps in section 218.9(a)(3) can protect you from penalties and liquidated damages. They do not erase liability for the unpaid wages themselves plus interest. That distinction needs to be in your payment file, not just in your head.
You cannot contract out of section 218.9. Section 218.9(a)(5) says nobody may evade or negate its requirements. You can still put an otherwise lawful pass-through remedy in your subcontract so the sub owes you back for labor debts, penalties, and liquidated damages you have to pay.
Have a construction attorney review that clause.
The three records and payment steps control penalty exposure
To avoid penalties and liquidated damages, section 218.9(a)(3) requires three things.
First, you must monitor payment by periodically reviewing the subcontractor’s payroll records. The statute does not set a weekly or monthly schedule. It says “periodic.”
The records must contain, at a minimum, the wage statement information listed in Labor Code section 226(a). They must also be payroll records contemplated by section 1174.
Second, when you become aware that the sub failed to pay, you must “diligently take corrective action to halt or rectify the failure.” The statute specifically includes retaining sufficient funds due to the subcontractor.
On a small shop, the first sign is rarely a letter. It is a call to the number on your truck or yard sign. A worker you have never met asks who is paying them for the trench they dug on your job. Or a GC’s office asks for “certified payroll” or the sub list before releasing a progress payment.
That call matters. Knowledge of nonpayment is one trigger for penalties. Once you are aware, section 218.9(a)(3)(B) requires diligent corrective action. Start retaining funds and asking for payroll records when the call comes in. Do not put it on next week’s list.
Third, before final payment to the subcontractor, you must obtain an affidavit signed under penalty of perjury. The affidavit must state that the sub paid the wage, fringe, or other benefit payment or contribution due to the employees or the labor trust fund for all work performed on the project.
No affidavit means no final payment if you want to complete that statutory step.
Your subcontract must name the records before you can withhold payment
When a direct contractor requests them, the subcontractor and any lower-tier subcontractors under contract to it must provide payroll records under section 218.9(f)(1).
The records may redact Social Security numbers, but they must show the last four digits. They must also show the subcontractor’s status on fringe or benefit payments to third parties.
The request can also cover award information under section 218.9(f)(2):
- Project name.
- Name and address of the subcontractor and upper-tier contractor.
- Anticipated start date.
- Duration.
- Estimated journeyman and apprentice hours.
- Contact information for the subcontractor’s own subcontractors.
Section 218.9(f)(3) says a sub’s failure to provide records does not relieve the direct contractor of its obligations. You cannot treat a missing response as a clean bill of health.
But section 218.9(h) gives the direct contractor a payment remedy. Prompt-payment duties under Civil Code sections 8800, 8812, 8814, and 8818, and Business and Professions Code section 7108.5, still apply. The exception is that the direct contractor may withhold as “disputed” all sums owed if the subcontractor does not timely provide the requested information, until the information is provided.
The statute does not give a number of days. It says “timely.”
Section 218.9(i) sets the contract requirement. To use this withholding right on a contract entered into on or after January 1, 2026, your subcontract must specify the specific documents and information you will require.
That makes your document list part of the payment system. It also belongs next to your other private-works payment procedures, including the issues covered in Wirewoman’s guide to private-works change order claim deadlines.
A subcontractor may put the same terms in its own lower-tier subcontracts and use the same withholding remedy.
Three kinds of plaintiffs can sue, and they get one year
The Labor Commissioner can enforce section 218.9 through a Labor Code section 98 hearing, a section 1197.1 citation, or a civil action. The Commissioner must give at least 30 days’ notice before a hearing, citation, or suit.
A person or entity described in Civil Code section 8024(a) can also sue. A prevailing plaintiff can recover reasonable attorney’s fees and costs, including expert witness fees. A joint labor-management cooperation committee under the federal Labor Management Cooperation Act of 1978 can bring an action after at least 30 days’ notice by first-class mail.
“No other party may bring an action against a direct contractor to enforce the liability,” under section 218.9(b)(4).
The Division of Labor Standards Enforcement must notify the direct contractor and the sub within 15 days after receiving a complaint.
An action must be filed within one year of the earliest of three events:
- Recording a notice of completion under Civil Code section 8182.
- Recording a notice of cessation under Civil Code section 8188.
- Actual completion of the work covered by the direct contract.
Those same notice dates can affect your mechanics lien deadlines as an electrician. Keep the project completion record with the payroll file.
Union fringe contributions have one narrow joint-check safe harbor
Section 218.9(b)(8) provides a safe harbor for fringe or benefit contributions.
If you have documentation that a benefit trust or fund told the subcontractor it missed contributions, you can avoid liability for those fringe contributions by paying with a joint check payable to both the subcontractor and the trust or fund.
Before doing that, the subcontractor must provide the fund’s name, type, number, and address. You must also notify the fund that you paid with a joint check.
This provision applies only to fringe and benefit contributions. It is mostly relevant to union subcontractors.
Wirewoman puts the first notice in a dated record
Wirewoman answers your line 24/7. Within 30 seconds of hang-up, she texts you the caller’s name, the problem in the caller’s own words, and the urgency. Every call is logged to a dashboard.
So when a sub’s worker calls about a missing paycheck, or a GC’s office asks for payroll records before payment, you receive a dated text in the caller’s own words while you are still on the job. The dashboard shows when you were told.
Wirewoman does not give legal advice, track payroll, or store payroll documents. It gives you a record that the call reached your business and when it reached you.
Change your subcontract and payment file this week
If you are the direct contractor, open your subcontract template now.
Add a clause listing the specific documents you will require:
- Payroll records containing the section 226(a) information and the last four digits of each Social Security number.
- Fringe and benefit payment status.
- The award information listed in section 218.9(f)(2).
- A final affidavit under penalty of perjury before final payment.
You must name the documents to use the withholding right under section 218.9(i). Add a lawful pass-through remedy under section 218.9(a)(5), then have a construction attorney review the wording.
Ask for payroll records periodically during the job. Each progress payment is a workable shop habit, but the statute itself only says “periodic.” Do not release final payment without the signed affidavit.
If you are the subcontractor, expect the GC’s request. Keep payroll records showing the section 226(a) items ready to send. Read the documents list in your subcontract. A late response can let the GC hold all sums owed as disputed.
Also confirm whether the people you call subs are really independent subcontractors. If they are your helpers, review Wirewoman’s guide to misclassification and 1099 electricians. For home improvement work, check whether your contract discloses whether you will use subcontractors.
Finally, calendar the one-year deadline from the notice of completion, notice of cessation, or actual completion, whichever occurs first.